1Material
Name, form (powder, granule, pellet), bulk density and particle size.
Calculator
Free pneumatic conveying calculator: airflow from pipe diameter and air velocity, solids loading ratio, and whether you are in the usual 18 to 35 m/s dilute phase band.
Airflow calculator
Set the pipe size, the air velocity and the material rate. See the airflow, the solids loading and whether the velocity sits in the usual dilute phase band.
*Indicative only. Airflow = pipe area × air velocity. Solids loading = material mass flow ÷ air mass flow, with air at 1.2 kg/m³. Air expands along a long line and pressure drop, bends, lift and material behaviour change the real design, so we size every line from your material data.
How the numbers work
Airflow is the pipe cross-section multiplied by the air velocity. Solids loading is the material mass flow divided by the air mass flow, with air taken at 1.2 kg/m³.
Cross-section of the pipe times the conveying velocity gives the volume of air per minute your blower must deliver at that point.
The ratio of material to air by mass. A higher ratio means a heavier load on the air stream and a higher pressure drop.
Dilute phase lines normally run at 18 to 35 m/s. Below that, material can settle and block the line. Above it, wear and breakage rise.
What it leaves out
Air expands along a long line. Bends, vertical lift, material behaviour, feeder losses and filter resistance all add pressure drop. That is why we size every line from your material data and why we ask for a layout sketch.
Saltation velocity is the minimum gas speed required to keep solid particles suspended in a horizontal conveying pipe. If line air velocity drops below saltation at the pickup zone, solids settle onto the pipe floor, shrink the open cross-section, and trigger a full plug. For stable operation, engineers size the pickup velocity roughly 20% to 30% above saltation, typically holding 18 to 22 m/s for fine free-flowing powders (fly ash, starch, wheat flour), 22 to 26 m/s for polymer pellets and resins (PVC, PP, HDPE), and 26 to 34 m/s for dense minerals such as cement, lime, and silica sand. Running much faster than required accelerates bend erosion and product breakage without increasing capacity.
The solids loading ratio (SLR or mu) compares the mass flow rate of bulk solids (kg/s) to the mass flow rate of conveying air (kg/s) at standard density (1.20 kg/m3 at 20 C). Conventional dilute-phase systems operate cleanly between 1:1 and 12:1, occasionally reaching 15:1 on short, lightly loaded positive-pressure lines using Roots blowers. Once SLR climbs past 15:1 to 20:1, high suspension friction exceeds centrifugal blower pressure limits and moves the duty into dense-phase plug or slug flow. Review the operating boundary in our dilute-phase vs dense-phase comparison before finalizing pipe bore.
Pipe diameter and pickup airflow only represent the starting input. Selecting the air mover requires summing six distinct pressure losses across the complete loop: Delta P_total = Delta P_air + Delta P_accel + Delta P_solids + Delta P_bends + Delta P_lift + Delta P_collector. Particle acceleration at the rotary airlock tee and re-acceleration after every 90-degree long-radius elbow consume major static head, where each elbow typically adds the equivalent friction of 10 to 15 metres of straight pipe. Vertical elevation lift adds static suspension head (rho_susp * g * H), while the receiver cyclone and pulse-jet baghouse add another 1,000 to 2,000 Pa (100 to 200 mmWC). Walk through step-by-step sizing math inside pneumatic conveying design calculation basics and our engineering breakdown on pneumatic conveying system price and design calculation.
Textbook air tables specify 20 C standard air, yet Indian factory utility bays routinely see 40 to 45 C ambient intake temperatures during summer afternoons. Because hotter air is less dense, the blower must pull higher actual intake volume: Q_actual = Q_std * ((273.15 + T_amb) / 293.15), adding roughly 8.5% volume at 45 C to deliver identical air mass down the pipe. Positive-pressure lines also lose 10% to 15% of conveying air upward past rotary airlock rotor tip clearances. Always include both allowances before locking blower kW, as explained in our guide on how to choose a blower for pneumatic conveying.
Before we quote
Do not worry if you do not have all of them. Send what you know, a rough sketch helps, and our engineers will ask for the rest.
Name, form (powder, granule, pellet), bulk density and particle size.
Moisture, temperature at the feed point, and whether it is abrasive, corrosive, sticky or hygroscopic.
Throughput in kg/hr, average and peak.
Horizontal run and vertical lift in metres, and the number of bends.
Number of pickup points and delivery points.
Power supply, space limits, a layout sketch, and any GMP, ATEX or CPCB requirements.
Send your numbers with the material details. We will size the line properly and reply within one working day.